CompTIA Project+ PK0-004 – Question596

A project team has just implemented an approved change to a project.
Which of the following should occur NEXT?

A.
Validate the change.
B. Evaluate the impact of the change.
C. Implement a regression plan.
D. Update the issue log.

Correct Answer: B