CompTIA Project+ PK0-004 – Question603

In a highway construction project, the project team has identified the need to utilize additional land for staging equipment.
After documenting the change request, which of the following should be accomplished NEXT?

A.
Communicate with the stakeholders
B. Audit the documentation
C. Obtain approval
D. Identify the approval authority

Correct Answer: D