Which of the following is MOST commonly associated with the WBS and used to develop a project timeline?

A.
Process diagram
B. RACI matrix
C. Gantt chart
D. Network diagram

Correct Answer: C

Explanation:

Explanation:
Gantt charts can show milestones, deliverables, and all the activities of the project including their durations, start and end dates, and the resources assigned to the task. Gantt charts typically display the tasks using a horizontal bar chart format across a timeline. I know project managers who have constructed Gantt charts for small projects using only a spreadsheet.