CompTIA Project+ PK0-004 – Question608 Which of the following is responsible for key decisions within a project?A. Project managerB. Project championC. Project management officeD. Project team Show Answer Hide Answer Correct Answer: A Explanation: Reference: https://www.pmi.org/learning/library/pm-decision-making-analysis-in… Post navigation CompTIA Project+ PK0-004 – Question607CompTIA Project+ PK0-004 – Question609