A project to implement Voice over Internet Protocol for a contact center has been expanded to include the entire organization.
Which of the following BEST describes the constraints involved?

A.
Deliverables, schedule, and resources
B. Stakeholders, scope, and schedule
C. Schedule, quality, and deliverables
D. Resources, requirements, and scope

Correct Answer: B