CompTIA Project+ PK0-004 – Question624

A project team member informs the project manager that a task on the critical path will not be completed on time.
Which of the following documents will MOST likely be updated? (Choose two.)

A.
Project scope
B. Project charter
C. Project schedule
D. Risk register
E. Incident response plan
F. Communication plan

Correct Answer: CD