CompTIA Project+ PK0-004 – Question631

While working with a project team to create the project schedule, which of the following must occur for performance measurement?

A.
Identify resource costs
B. Manage issues
C. Create status reports
D. Set the baseline

Correct Answer: D

Explanation:

Explanation:
The project management plan contains the project management baseline data (typically cost, schedule, and scope), which you’ll use to monitor and compare performance measurements against.