Which of the following is the burn rate of a project?
A. The amount of project staff turnover over time
B. The positive cash flow of the project for the organization over time
C. The amount of expenditures supporting the project over time
D. The amount of capital spent to ensure quality of the project deliverables
A. The amount of project staff turnover over time
B. The positive cash flow of the project for the organization over time
C. The amount of expenditures supporting the project over time
D. The amount of capital spent to ensure quality of the project deliverables