CompTIA Project+ PK0-004 – Question644

A testing event was held and deemed unsuccessful. After review, it becomes clear that the two project teams had different expectations of the testing.
Which of the following is needed between the two teams?

A.
Communication plan
B. Project schedule
C. Status report
D. Use case

Correct Answer: A