CompTIA Project+ PK0-004 – Question648

In a projectized organization, which of the following occurs FIRST at the completion of a project?

A.
Resources are allocated to the PMO.
B. Resources are assigned to new projects.
C. Resources are transferred to operations.
D. Resources are released to functional managers.

Correct Answer: B

Explanation:

Explanation:
One of the biggest drawbacks of a projectized organization is reassigning project team members once the project ends. There may not always be a new project waiting for these resources.