CompTIA Project+ PK0-004 – Question671

A company accepts a proposal from a third-party vendor to provide staffing. Which of the following documents should the project manager create NEXT?

A.
SLA
B. SOW
C. LOI
D. RFQ

Correct Answer: C

Explanation: