CompTIA Project+ PK0-004 – Question675

Input into a project's requirements is needed for clarification. With which of the following roles would the project manager MOST likely consult?

A.
Project risk manager
B. Project stakeholder
C. Project scheduler
D. Project coordinator

Correct Answer: B