CompTIA Project+ PK0-004 – Question681

During an active project, a meeting is set up to explain new internal processes. Which of the following MOST likely triggered this meeting?

A.
The scope of the project changed.
B. The sponsor requested additional functionality.
C. A project team member left the organization.
D. The PMO standard requirements changed.

Correct Answer: D