A project coordinator holds a status meeting about a new product line. Some deliverables are behind schedule and need to be completed over the weekend. As a result, extra effort may be needed to adhere to the project timeline. Which of the following project phases is occurring?
A. Monitoring
B. Initiating
C. Planning
D. Closing