A project manager needs a systems administrator as a resource on a project. The project manager approaches the operations manager to obtain the resource. In which of the following organizational structures is the project manager MOST likely operating?

A.
Hybrid
B. Projectized
C. Functional
D. Matrix

Correct Answer: B