CompTIA Project+ PK0-004 – Question688

A project manager has laid out a network diagram and is beginning to schedule activities for an upcoming project. Which of the following activities should be performed LAST?

A.
Determine the start/finish dates.
B. Determine the critical path.
C. Determine the dependencies.
D. Determine the task durations.

Correct Answer: B