CompTIA Project+ PK0-004 – Question703 Which of the following indicators will assist the project manager in determining the health of the budget?A. SVB. CPIC. ACD. EVE. ETC Show Answer Hide Answer Correct Answer: D Explanation: Reference: https://pmstudycircle.com/planned-value-pv-earned-value-ev-actual-c… Post navigation CompTIA Project+ PK0-004 – Question702CompTIA Project+ PK0-004 – Question704