CompTIA Project+ PK0-004 – Question706

Given the status report excerpt below:

Overall status: The project is tracking well. Tasks are being completed on time. Costs are lower than expected.
Risk/issues are regularly being monitored are tracked.
Which of the following MOST likely is occurring in the project?

A.
The project manager forgot to update the risks/issues status.
B. The project has experienced a risk trigger recently that may impact the project very soon.
C. There is nothing out of the ordinary; the project is progressing as expected.
D. The project manager did not include any risks/issues detail because it is yellow and not red.

Correct Answer: B