CompTIA Project+ PK0-004 – Question714

A project manager has just received an extra resource from a functional manager. Which of the following activities is the BEST to consider for assignment to the resource?

A.
Activity A should be assigned because it is within the resource's skillset, has already been started with three other resources, and has four days of slack.
B. Activity B should be assigned because it is not within the resource's skillset; however, it gives the resource an opportunity to learn a new skill, has not started, and has one day of slack.
C. Activity C should be assigned because it is a task that any resource can do; however, it is undesirable, needs to be done, has not started, and has three days of slack.
D. Activity D should be assigned because it is a new task, the skillset determination has not been assessed for the task, it is supposed to start tomorrow, and it has zero slack.