CompTIA Project+ PK0-004 – Question721

A project manager has established a series of virtual meetings with project team members in different parts of the world. Team members from one country almost never show up to the meeting. Which of the following MOST likely describes why this occurring?

A.
There is no rapport between the team members and the project manager.
B. The time zone in the one country is outside of working hours.
C. The meeting is occurring too frequently.
D. Language barriers prevent team members from participating.

Correct Answer: B