CompTIA Project+ PK0-004 – Question727

A vendor notifies the project manager that the scheduled date for a deliverable on the critical path cannot be met due to a lack of resources. Which of the following are MOST likely to be triggered? (Choose three.)

A.
Milestones
B. Stakeholder changes
C. Audits
D. Schedule changes
E. Incident response
F. Business continuity response
G. Risk register updates

Correct Answer: ADG