The project manager for a multinational project is evaluating the option of scheduling face-to-face meetings during the release of a new system. The goal is to provide 24/7 coverage and quick responses to issues. Which of the following strategies is being applied?
A. Risk acceptance
B. Risk avoidance
C. Risk transference
D. Risk mitigation