CompTIA Project+ PK0-004 – Question750

A highly experienced resource, who is working in the network security department, needs to be allocated to a project. The project manager wants to negotiate the terms of participation with the resource, but the network coordinator denies the request. Which of the following organizational structures BEST describes this scenario?

A.
Projectized
B. Hybrid
C. Strong matrix
D. Functional

Correct Answer: C