CompTIA Project+ PK0-004 – Question759

A project manager has been overseeing an effort to build and design a new satellite-based navigation system for autonomous agriculture machines. Because of the inherent dangers related to the autonomous control of heavy machinery, gate reviews were scheduled at regular intervals, but they failed. Which of the following resource management issues MOST likely affected the project?

A.
Shared resources
B. Inter-project dependencies
C. Resource shortages
D. Low-quality resources