A project stakeholder identifies a need for a vendor to provide 24-hour support for a product under development. Which of the following BEST describes where this information would be documented?
A. Service-level agreement
B. Purchase order
C. Statement of work
D. Project charter
A. Service-level agreement
B. Purchase order
C. Statement of work
D. Project charter