A deliverable is coming due, but the project team is falling behind. Meetings happen only once a month, preventing the team from understanding current project progress. Which of the following strategies should the project manager use to focus the team on the deliverable?

A.
Gate reviews
B. Change control
C. Status reports
D. Daily stand-ups

Correct Answer: D