A new project has started, and the project schedule is being built. After the WBS is complete, scheduling of the activities begins. Which of the following is the most likely NEXT step?

A.
Sequence the activities.
B. Allocate the resources.
C. Set the baseline.
D. Determine the tasks.

Correct Answer: A