CompTIA Project+ PK0-004 – Question792

A project team identifies the fluctuating cost of a raw material as a risk to the project. Just prior to procuring the material, the price drops substantially. The team decides to double the order of the material and use the surplus in a future project. Which of the following risk strategies does this employ?

A.
Mitigate
B. Exploit
C. Accept
D. Transfer

Correct Answer: A