CompTIA Project+ PK0-004 – Question800

A customer requests an additional requirement for the finished product. After the change is identified and documented, which of the following would be the NEXT step in the process?

A.
Update the project documents to show the change.
B. Evaluate the impact of the change.
C. Implement the requested change.
D. Submit the change request for approval.

Correct Answer: C

Explanation:

Explanation:
After accepting the request, the need to implement the requested chance should be at priority for time and cost management.