CompTIA Project+ PK0-004 – Question800

A customer requests an additional requirement for the finished product. After the change is identified and documented, which of the following would be the NEXT step in the process?

A.
Update the project documents to show the change.
B. Evaluate the impact of the change.
C. Implement the requested change.
D. Submit the change request for approval.

Correct Answer: C

Explanation:

Explanation:
After accepting the request, the need to implement the requested chance should be at priority for time and cost management.

CompTIA Project+ PK0-004 – Question796

A project team has deliverables that are scheduled to take several weeks to complete. The project manager is concerned that procrastination will set in. Which of the following should the project manager do?

A.
Allocate the resources.
B. Prioritize the tasks.
C. Review the milestones.
D. Set the dependencies.

Correct Answer: B

CompTIA Project+ PK0-004 – Question795

A change request has been submitted to change the construction material from cinder block to wood frame.
Which of the following should be performed FIRST after the change has been approved by the sponsor?

A.
Documentation update and review
B. Quality check
C. Team approval
D. Impact analysis

Correct Answer: A

CompTIA Project+ PK0-004 – Question794

A project to develop a new ordering system will require the procurement of additional equipment. During which of the following project phases would procurement be considered?

A.
Planning
B. Initiation
C. Monitor and control
D. Execution

Correct Answer: A

CompTIA Project+ PK0-004 – Question793

A project manager receives feedback that a team member is not sharing best practices with the team so they can do their work faster. The project manager sees a bowling trophy at the team member's desk, and invites the team member to go bowling and have a one-on-one conversation. Which of the following describes the project manager's approach?

A.
Personal preferences
B. Cultural differences
C. Rapport building
D. Team building

Correct Answer: C

CompTIA Project+ PK0-004 – Question792

A project team identifies the fluctuating cost of a raw material as a risk to the project. Just prior to procuring the material, the price drops substantially. The team decides to double the order of the material and use the surplus in a future project. Which of the following risk strategies does this employ?

A.
Mitigate
B. Exploit
C. Accept
D. Transfer

Correct Answer: A