CompTIA Project+ PK0-004 – Question669

During an active project, the finished deliverables become subject to new regulatory standards, and a new testing process must be included. Which of the following constraints is influencing this project?

A.
Scope creep
B. Resources
C. Quality
D. Requirements

CompTIA Project+ PK0-004 – Question668

A functionality managed project is falling behind schedule, and the project manager asks the team to work without interruption until the project is back on track. The functional manager refuses to allow the team to be isolated from other work. Which of the following steps should be taken FIRST to help put the project back on track?

A.
The functional manager should assume the risk to the timeline.
B. The project manager should assign additional resources to the project.
C. The project manager should escalate the issue to gain full attention.
D. The functional manager should agree to dedicate a portion of each day to the project.

Correct Answer: C

CompTIA Project+ PK0-004 – Question666

The sponsorship of an active project has changed multiple times, and stakeholders have submitted a large number of change requests. Which of the following would be the BEST method to rebaseline the project?

A.
Mandatory meeting
B. Stand-up meeting
C. FAQ about the project
D. Detailed status report

Correct Answer: D

CompTIA Project+ PK0-004 – Question664

Which of the following is performed during the monitoring and controlling phase?

A.
Quality control and training plan development
B. Creation of schedule and fund deliverables
C. Development of transition plan and finalizing contracts
D. Quality assurance and governance oversight

Correct Answer: D

CompTIA Project+ PK0-004 – Question662

A project manager is leading a project that has global personnel resources. Which of the following would be the MOST appropriate manner for the project team to share accurate, complete, and important project information and updates while ensuring the team is participating?

A.
Email
B. Text message
C. Video conference
D. Instant message

Correct Answer: A