CompTIA Project+ PK0-004 – Question640

A project manager and a project sponsor have agreed to accept all risks that have a low impact and low probability. Given the information below:

Which of the following risks from the risk register should have an acceptance strategy? (Choose two.)

A.
1
B. 2
C. 3
D. 4
E. 5
F. 6

Correct Answer: DF

CompTIA Project+ PK0-004 – Question639

A project is out of control because project team members are completing tasks based on preference and suggestions from project stakeholders, instead of following the project schedule.
Which of the following is an indication that this project is out of control?

A.
Stakeholders are not properly engaged.
B. There is no project manager named.
C. Performance relative to the plan is unknown.
D. Work is being accomplished faster than planned.

Correct Answer: C

CompTIA Project+ PK0-004 – Question638

During a project status meeting, the project manager states the project is running ahead of schedule. However, the executive committee, which is unfamiliar with the project manager's work, does not think it will finish on time.
Which of the following is the MOST likely cause?

A.
personal preferences
B. Interorganizational differences
C. Relationship building
D. Specific communication

Correct Answer: D

CompTIA Project+ PK0-004 – Question637

A finance company hired a software consulting company to develop a new system. During the testing phase, the finance company's testing team found a major defect. The software consulting company states the software was constructed per the approved design.
Which of the following documents should be used to clarify the situation?

A.
Letter of intent
B. Requirements document
C. Statement of work
D. Service-level agreement

Correct Answer: D

CompTIA Project+ PK0-004 – Question635

A project manager is planning a wedding that will take place during the rainy season. The possibility of rain is very high, so the project manager proposes alternatives to having an outdoor wedding.
This is an example of:

A.
mitigation.
B. acceptance.
C. exploitation.
D. transference.

Correct Answer: A

Explanation:

Explanation:
Mitigation is to reduce the probability or impact of a risk.

CompTIA Project+ PK0-004 – Question634

Which of the following is the burn rate of a project?

A.
The amount of project staff turnover over time
B. The positive cash flow of the project for the organization over time
C. The amount of expenditures supporting the project over time
D. The amount of capital spent to ensure quality of the project deliverables

Correct Answer: C

Explanation:

Explanation:
Burn rate is the rate you are spending money over time. For example, if you had a $12,000 budget and you’re spending $2,000 a month, you’ll run out of money in six months.

CompTIA Project+ PK0-004 – Question633

Management announces the PMO will assume all research and development efforts.
Which of the following BEST describes this scenario?

A.
Process change
B. Business merger
C. Outsourcing
D. Relocation

Correct Answer: A

Explanation:

Explanation:
Business process changes typically occur within the organization. An example of a business process change is automating a process that previously was performed on paper. If your project has anything to do with this process or is impacted by the process, changes will be coming your way.

CompTIA Project+ PK0-004 – Question631

While working with a project team to create the project schedule, which of the following must occur for performance measurement?

A.
Identify resource costs
B. Manage issues
C. Create status reports
D. Set the baseline

Correct Answer: D

Explanation:

Explanation:
The project management plan contains the project management baseline data (typically cost, schedule, and scope), which you’ll use to monitor and compare performance measurements against.