When a project milestone is completed, which of the following activities ensures the quality of the deliverables at that point in the project? A. Gate review B. Lessons learned C. Audit D. Baseline review
A project team has identified project risks and is determining the likelihood and impact of these risks. Which of the following BEST characterizes this activity? A. Response B. Prioritization C. Quantification D. Review
A project team is spread across multiple countries and time zones. A change request has been approved by the CCB. Which of the following is the BEST way to communicate the approval? A. Email B. Instant message C. Weekly project meeting D. Intranet posting
A project manager is concerned that a planned change might damage the key functionality of a major system.
The MOST important activity to perform is: A. a quality control check. B. an in-depth impact evaluation. C. software version control. D. a regression plan.
Which of the following BEST describes a subject matter expert who is solicited for input during the development of a product? A. Sponsor B. Coordinator C. Stakeholder D. Assistant
Three months into a project, the project sponsor asks the project manager for the amount of money that has been spent on the project at that point. The project sponsor is asking for the: A. AC B. ROI C. BAC D. CPI
A project manager is overseeing a project to launch a new satellite. While the satellite is being developed internally, a required piece to launch the system is provided by an external partner, which has experienced a high failure rate. Which of the following risk strategies should the project manager apply? A. Transfer the risk with an insurance plan to cover potential failures. B. Avoid the risk by building the launch system internally. C. Accept the risk as normal for this type of project. D. Mitigate the risk by requiring quality checkpoints.
A quality manager is detailing performance results, which show an exponential trend. Which of the following tolls should be used to demonstrate this visually? A. Scatter chart B. Gantt chart C. Run chart D. Pareto chart
A new project has started, and the project schedule is being built. After the WBS is complete, scheduling of the activities begins. Which of the following is the most likely NEXT step? A. Sequence the activities. B. Allocate the resources. C. Set the baseline. D. Determine the tasks.
Halfway through a project, the project manager is told it needs to be completed four weeks earlier than originally planned. Which of the following will MOST likely be impacted to accomplish this goal? A. Risks B. Budget C. Quality D. Deliverables
Correct Answer: B