CompTIA Project+ PK0-004 – Question590

A project team is brainstorming and documenting what might go wrong in a project, the possible impact, and potential actions should certain situations arise.
Which of the following contains actions the team is MOST likely to consider?

A.
Identify, collaborate, quantify
B. Accept, mitigate, transfer
C. Stop, review, plan
D. Prioritize, qualify, engage

Correct Answer: A

Explanation:

CompTIA Project+ PK0-004 – Question588

A project manager has requested the procurement department collect detailed solutions with cost estimates from qualified third-party vendors.
This is an example of an:

A.
MOA
B. RFP
C. RFI
D. RFQ
E. MOU

Correct Answer: D

Explanation:

Explanation:
RFIs and RFQs may be used interchangeably but may also have different meanings in different organizations, so make certain you understand which document to use according to your organization’s process. Regardless of what these documents are called, they should include your SOW, information regarding how responses are to be formatted and delivered, and a date by which responses must be submitted. Potential vendors may also be required to make a formal presentation, or they may be asked to submit a bid.

CompTIA Project+ PK0-004 – Question587

A project manager notices several of the action items discussed during a team-building exercise have been ignored by the project team. Although the team-building exercise was well attended and feedback was well received, nothing was accomplished.
To make the meetings more productive, which of the following steps should the project manager take? (Choose two.)

A.
Get suggestions from the project sponsor.
B. Schedule more frequent meetings.
C. Take meeting minutes.
D. Post an agenda prior to starting the meeting.
E. Schedule face-to-face meetings.
F. Make the meetings mandatory.

Correct Answer: CD

CompTIA Project+ PK0-004 – Question586

A company is about to initiate a cybersecurity project. However, the project manager realizes the company does not possess the required skills to complete the project and requires a search by third-party vendors.
Which of the following documents should the project manager provide?

A.
RFI
B. LOI
C. RFP
D. RFQ

Correct Answer: A

Explanation:

Explanation:
An RFI is used when you need to gather more information about the goods or services you need to procure.
This process will give you a sense for the number of providers or contractors who can provide the goods or services, and you will get an idea of cost. An RFI or RFQ is used when the costs are unknown to you and you need an estimate for the goods or services.

CompTIA Project+ PK0-004 – Question584

A project, which is nearing completion, is ahead of schedule and under budget. However, to improve quality to acceptable levels, the project will require additional time.
Which of the following BEST describes this scenario?

A.
Score creep
B. Interactions between constraints
C. Constraint reprioritization
D. Change request

Correct Answer: B

Explanation:

Explanation:
An example of interaction between constraints may occur when you have changes to scope that in turn impact the schedule and/or budget. Scope can change through the formal change control process or through scope creep. Perhaps your project sponsor has decided you need one more deliverable in order to satisfy the overall goals and objectives of the project. This is approved in a formal change request process. However, scope changes require schedule changes, and they often require budget changes as well. The interaction here is like a domino effect, and all the constraints should be reexamined to ensure that they still accurately reflect the conditions of the project.

CompTIA Project+ PK0-004 – Question583

Ann, a customer, approaches the project manager of a portable computing device implementation project with a request to have a tablet instead of a laptop.
Which of the following steps should the project manager take NEXT?

A.
Supply Ann with the requested tablet.
B. Have Ann submit a change request.
C. Provide Ann with a copy of the project management plan.
D. Inform Ann that she will receive what has been authorized.

Correct Answer: A

CompTIA Project+ PK0-004 – Question581

A project team is preparing for a major system upgrade that is scheduled for next week. During the upgrade, there will be limited availability of technology resources.
Which of the following is the BEST communication method for the team during the activation?

A.
In-person command center
B. Video conferencing
C. Voice conferencing
D. Instant messaging

Correct Answer: D

Explanation:

Explanation:
Instant messaging allows you to communicate with another person via a text message over the Internet. There are many software programs that provide this capability. You can use instant messaging on a computer, tablet, or phone provided the software program you’re using has that capability. It’s a great mechanism to convey a quick, short message. Instant messaging isn’t appropriate for meetings or complex information or for communicating with multiple people at the same time.