CompTIA Project+ PK0-004 – Question470

The project team has identified all the tasks needed to create project deliverables and grouped them into work packages covering all project scope. Which of the following should be done NEXT?

A.
Identify task relationships.
B. Put the resources on tasks.
C. Set the quality gates.
D. Estimate the work package.

Correct Answer: D

CompTIA Project+ PK0-004 – Question469

Which of the following are characteristics of qualitative risk assessments as opposed to quantitative? (Choose two.)

A.
Qualitative assessments are more difficult.
B. Qualitative assessments are faster.
C. Qualitative assessments require fewer resources.
D. Qualitative assessments provide more accurate results.
E. Qualitative assessments better identify opportunities.

Correct Answer: BC

CompTIA Project+ PK0-004 – Question468

A company has completed its annual strategic planning session. As a result, several related projects, which will achieve the company's technological improvement goals, are identified. Which of the following BEST describes these projects?

A.
Portfolio
B. Program
C. Deliverable
D. Outcome

Correct Answer: B

CompTIA Project+ PK0-004 – Question465

Tasks A, B, and C have a duration of two days. Task D has a duration of three days, and Task E has duration of four days. Task A starts on Day 1, and Task B starts on Day 2. Task C starts after Task A. Tasks D and E start after Task C. Which of the following is the critical path if Task B starts on Day 3?

A.
A, C, D
B. A, C, E
C. A, D, E
D. B, C, E

Correct Answer: B

CompTIA Project+ PK0-004 – Question464

A company recently went through a project requiring new equipment, new software, and retraining of personnel.
This is MOST likely a result of:

A.
an internal reorganization.
B. outsourcing.
C. a business process change.
D. resource allocation.

Correct Answer: C

CompTIA Project+ PK0-004 – Question462

A hurricane occurs in an area where several key project resources are located. When reviewing the project dashboard, the project sponsor sees the project is behind schedule and asks the project manager for an explanation. Which of the following documents should the project manager examine NEXT to provide an explanation?

A.
Meeting minutes
B. Issue log
C. Project schedule
D. Budget

Correct Answer: B

CompTIA Project+ PK0-004 – Question461

A key stakeholder has communicated a significant project scope change to the project manager. Which of the following actions should the project manager take FIRST?

A.
Submit a change request to the CCB.
B. Implement the change to the project.
C. Determine the impact of the requested change.
D. Update the schedule to accommodate the change.

Correct Answer: C