CompTIA Project+ PK0-004 – Question409

A project manager is collecting the number of hours, the resources, and the amount of money spent on hardware and software. Which of the following is MOST likely the purpose of collecting this information?

A.
Financial stability
B. Competitive advantage
C. Budget constraints
D. Expenditure tracking

Correct Answer: D

CompTIA Project+ PK0-004 – Question408

A key stakeholder cannot identify within the resource management plan where the project manager has authority to assign resources. Which of the following should the project manager use to answer the question?

A.
Project schedule
B. Project management plan
C. Project charter
D. Staffing matrix

Correct Answer: B

CompTIA Project+ PK0-004 – Question407

A project manager is planning to hold a meeting to discuss what went well, what did not go well, and what should be done differently. Which of the following meetings should the project manager hold?

A.
Kickoff
B. Impromptu
C. Closure
D. Status

Correct Answer: D

CompTIA Project+ PK0-004 – Question402

After SOW and contract approvals, the project manager plans to schedule a meeting with the business analyst and several end users. The project manager's main objective in this meeting is to:

A.
identify resources
B. baseline the schedule
C. create deliverables
D. define requirements

Correct Answer: D