Which of the following is primarily responsible for developing the timeline? A. Project sponsor B. Project coordinator C. Project manager D. Project scheduler
Correct Answer: D
Explanation:
Explanation:
The project scheduler is responsible for developing and maintaining the project schedule, communicating the timelines and due dates, reporting schedule performance, and communicating any schedule changes to the stakeholders and project team members.”
– Kim Heldman CompTIA Project+ Study Guide; 2nd Edition; Sybex; Indianapolis.
Which of the following will MOST likely result in changes to the project plan? A. Departure of the project manager B. Departure of the sponsor C. Milestone realization D. Incident occurrence
Everyone on the team agrees with a change request, and the team proceeds with the implementation. Which of the following steps is missing from the identified process? A. Impact justification B. Formal approval C. Quality check D. Identify and document
A project team learns that potential remodeling on the production floor might occur during the execution phase of their project. The project team starts debating the different options available to keep delivering without adjusting the schedule. Which of the following risk activities is being performed? A. Mitigation B. Quantification C. Planning D. Identification
A security breach was identified within a large company. The authentication server crashed, and employees are unable to access their accounts. Which of the following project constraints will MOST likely be impacted by this issue? A. Timeline B. Quality C. Budget D. Scope
A project needs to know if a project is progressing as planned. Which of the following tools would be BEST to measure progress? A. Histogram B. KPI C. Pareto chart D. RACI matrix E. CPM
A project manager has just received an extra resource from a functional manager. Which of the following activities is the BEST to consider for assignment to the resource? A. Activity A should be assigned because it is within the resource's skillset, has already been started with three other resources, and has four days of slack. B. Activity B should be assigned because it is not within the resource's skillset; however, it gives the resource an opportunity to learn a new skill, has not started, and has one day of slack. C. Activity C should be assigned because it is a task that any resource can do; however, it is undesirable, needs to be done, has not started, and has three days of slack. D. Activity D should be assigned because it is a new task, the skillset determination has not been assessed for the task, it is supposed to start tomorrow, and it has zero slack.
A project sponsor is not being updated on the project as expected. Instead of receiving information on a monthly basis, the project sponsor wants to see it biweekly and requests the use of a collaboration site instead of email. Which of the following actions should the project manager perform? A. Update the project status report and inform the project team. B. Update the project charter and inform the project sponsor. C. Update the project management plan and review it at the next status meeting. D. Update the project communication plan and distribute it to the stakeholders.
Which of the following should receive regular communication during the planning phase of a project? (Choose two.) A. Collaboration site B. Change control board C. Subject matter experts D. Sponsor E. Human resources
Correct Answer: CD