CompTIA Project+ PK0-004 – Question012

A project requires daily status updates.
Which of the following is the MOST effective method for providing these updates?

A.
Backlog
B. Standup
C. Kickoff
D. Retrospective

Correct Answer: B

Explanation:

Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 306