CompTIA Project+ PK0-004 – Question023

The executive sponsor asks a project manager to summarize the following for a project:
1. Final capital expenditures.
2. Anticipated cost of new employee resources to support the solution.
3. Maintenance estimates.
Which of the following information should the project manager provide?

A.
Cost baseline
B. Burn rate
C. Cost variance report
D. Total project cost

Correct Answer: A