CompTIA Project+ PK0-004 – Question034

Assuming an iterative approach, which of the following will be conducted at the end of each iteration?

A.
SCRUM retrospective
B. Kickoff meeting
C. Budget baseline
D. Risk review

Correct Answer: A

Explanation:

Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 306