CompTIA Project+ PK0-004 – Question037 Which of the following metrics demonstrates to a project manager if a project is overspending or underspending?A. EACB. BACC. CPID. ETC Show Answer Hide Answer Correct Answer: C Explanation: Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 231