CompTIA Project+ PK0-004 – Question051

Which of the following project documents should be used to record the occurrence of an unplanned event?

A.
Action log
B. Risk log
C. Change log
D. Issue log

Correct Answer: D

Explanation:

Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 327