CompTIA Project+ PK0-004 – Question052

Which of the following documents does a vendor rely on MOST before committing funding and resources to a project?

A.
SOW
B. PO
C. SLA
D. MOU

Correct Answer: A

Explanation:

Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 299