CompTIA Project+ PK0-004 – Question052 Which of the following documents does a vendor rely on MOST before committing funding and resources to a project?A. SOWB. POC. SLAD. MOU Show Answer Hide Answer Correct Answer: A Explanation: Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 299