CompTIA Project+ PK0-004 – Question057

A customer has requested additional features for an active project.
Which of the following steps should take place NEXT?

A.
Implement the requested changes.
B. Evaluate the impact of the changes.
C. Update all project documents.
D. Submit the requested changes to the CCB.

Correct Answer: B

Explanation:

Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 293