A project manager is assigned to a new project that must start immediately. No formal or approved documents have been authored for the project. The project manager must identify project roles, justify the business need, and determine project scope boundaries.
Which of the following documents should the project manager create?
A. Business case
B. Project charter
C. Scope statement
D. Project management plan
Which of the following documents should the project manager create?
A. Business case
B. Project charter
C. Scope statement
D. Project management plan