CompTIA Project+ PK0-004 – Question072

A project manager needs to identify the resources assigned to a particular task.
In which of the following documents can this information be found?

A.
Project schedule
B. Cost plan
C. Scope statement
D. Impact assessment

Correct Answer: A

Explanation:

Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 156