A project team has purchased computers with warranties extending throughout the entire project. Which of the following represents the risk strategy utilized?

A.
Transfer
B. Share
C. Mitigate
D. Avoid

Correct Answer: C

Explanation:

Reference: https://www.simplilearn.com/risk-management-strategies-article