A project manager is providing the lessons learned for a project that ran over budget and produced poor quality deliverables. Which of the following should the project manager include as part of the lessons learned?

A.
Risk register
B. Post-mortem analysis
C. Issue log
D. Procurement report

Correct Answer: B

Explanation: