CompTIA Project+ PK0-004 – Question114

An outsourced project team member approaches the project manager and complains that the contract does not permit overtime. The project manager had fast-tracked tasks that require additional hours. Which of the following documents did the project manager fail to reference?

A.
MOU
B. MOA
C. SOW
D. SLA

Correct Answer: B