A new stakeholder has been added to a project with a BAG of $850,000. The stakeholder has raised five change requests to the CCB; two of them have been approved, and three are awaiting initial review.
Considering the project has a CPI of 0.89 and an SPI of 1.14, and the approved ones will be implemented, which of the following should the project manager do LAST?
A. Identify and document the risk.
B. Evaluate the impact and justification.
C. Implement the change.
D. Update the documents and plans.